AKENERJI ERZIN COMBINED CYCLE POWER PLANT
600.000 m² / 900 MW • Hatay (Erzin) (2013)
About the Project
Covering 600,000 m² with 900 MW installed capacity in Hatay, this landmark energy project coordinated EPC site progress, Primavera P6 master schedules, and contractor claims with model verification.
Services Rendered Across Project
- Primavera P6 Schedule Planning & Time Governance
- Model-Based Quantity Verification & BoQ Support
- Physical Progress Performance Audits & Schedule Alignment
Related Projects
ISTANBUL REGNUM VILLA ESTATE
286 Konut – Villa & Ticari Yapılar • İstanbul
RONESANS ISTANBUL SANCAKTEPE CITY HOSPITAL
Şehir Hastanesi – Cephe Sistemleri • İstanbul (Sancaktepe)
MERINOS MTR PROJECT
250.000 m² • Gaziantep
SASA PTA PRODUCTION COMPLEX
375 Dönüm • Adana (Seyhan)
TEIAS SUBSTATION SWITCHYARD PERIMETER FENCING
Trafo Merkezleri Şalt Sahaları • Kozan – Erzin – Hatay